25
Sat, Nov

South Hillside Avenue, Roxbury: Roadwork Expect Delays

Landing \ Roxbury News
Typography
  • Smaller Small Medium Big Bigger
  • Default Helvetica Segoe Georgia Times

The 2.6-mile project will run from Eyland Avenue to Route 10. Topline Construction of Somerville will be the contractor. The bid price is $534,147. The project, scheduled to start on Aug. 14, includes storm basin work, milling, paving and striping. Work is expected to occur from 7:30 a.m. to 4:30 p.m. Motorists should expect traffic delays. The contractor has 20 working days (in good weather) to complete the work.

Join us on Facebook

Upcoming Events